"However, the project still is on target for a late 2012 completion,
said bankruptcy court trustee Mike Boudloche. He was appointed by the
U.S. Bankruptcy Court overseeing the ASARCO Inc. and Encycle/Texas Inc.
bankruptcy cases.

"We are almost finished with the asbestos removal on the stack and will
begin bringing it down the first week of December," Boudloche said on
Thursday.

The 315-ft tall, asbestos-lined stack, the most visible symbol of the
site's environmental problems, will be cut into pieces and hauled away,
he said."